Change orders in a van build: how to stop “can we just add…” eating your margin

· 6 min read

A change order is the priced, signed difference between the design your client approved and the one they now want — and the only reliable way to stop “can we just add…” eating your margin is to freeze an approved version before the first cut and measure every later request against it in cost, weight and hours. A shower and a second battery sound like two small extras. With a bigger water tank to feed the shower, they are about 100 kg, several hundred euros of parts and a day or more of plumbing and wiring — after the floor is already down.

Scope creep in a conversion is rarely one big change. It is five small ones, each asked for in the workshop doorway, each “just” something. Individually none is worth a conversation; together they are the difference between a job that paid and one that didn’t.

Freeze one version first

Nothing can be a change until something is agreed. The agreed thing has to be specific: the layout, every item in it, its size and position, and the price that went with it. A PDF quote attached to an email is a start; a frozen copy of the actual design is better, because the change order is then a comparison, not a recollection.

The rule I would put in every quote: the approved version is what the price covers; anything else is a change, priced before it is built. Clients accept this easily when they hear it on day one. They resent it when they first hear it on invoice day.

What a change actually costs

Every change has three prices, and builders usually only charge the first.

ChangePartsWeightHours
Added itemIts priceIts weight, at its positionFitting, plus whatever it connects to
Removed itemCredit (if not yet bought)Minus its weightRemoval if already fitted
Moved itemUsually noneSame total, different axle splitOften more than adding — re-routing, refixing
Resized itemDifferenceDifferenceRe-cutting, sometimes rebuilding neighbours

The weight column is the one clients never think about. Every kilogram lands somewhere between, over or behind the axles, and the lever rule decides how it splits: an item behind the rear axle loads it with more than its own weight and lifts weight off the front.

A worked example: “can we add a shower and a second battery?”

Take a Fiat Ducato L3H2 (front-wheel drive, 4.035 m wheelbase). Its kerb weight in the van database is 2,095 kg against a 3,500 kg gross — 1,405 kg for the whole conversion, the people and the luggage. The client approved a layout with a wardrobe and a 35 L fresh tank. Three weeks in, they ask for a shower and a second battery. To be usable, the shower needs more water, so the tank grows too.

The change order, using VanPlot’s default catalog parts (prices are planning defaults — your supplier’s replace them):

ItemChangeΔ weightΔ parts
Shower cubicleAdded+30 kg+€400
Shower drain pumpAdded+0.9 kg+€90
Battery 105 AhAdded (second)+12 kg+€280
Fresh tank 35 L → 125 LChanged (full weight)+92 kg+€40
WardrobeRemoved for the shower−35 kg−€150
Total≈ +100 kg+€660

A hundred kilograms is about 7 % of that Ducato’s pre-build payload, gone in one conversation. And where it goes matters as much as how much: if the extra 92 kg of water sits 0.5 m behind the rear axle, the rear axle carries about 103 kg more and the front about 11 kg less; the same tank 1 m ahead of the rear axle puts about 69 kg on the rear and 23 kg on the front. That is a placement decision the client should see before agreeing, not after the weighbridge. The weighbridge side is in proving payload and axle loads before the build. How much a conversion weighs and the payload reserve guide cover how much margin a build needs left for people, water and gear.

The hours are yours to price — you know how long your team takes to plumb a shower tray and drain, to parallel a second battery and re-fuse it, and to relocate a tank once the floor is in. Whatever the number, write it on the line. The build order is why late changes cost more: a shower added after the floor and walls is a shower that reopens them.

What goes on the change-order sheet

One page, signed or approved before the work starts:

  1. The baseline — which approved version this compares against, and its date.
  2. Every difference, item by item — added, removed, moved, resized — with before → after where something changed.
  3. Δ weight and Δ parts cost per line, with totals.
  4. Labour per line at your rate, and the new total price.
  5. The effect on the van — remaining payload and axle loads after the change, if they moved meaningfully.
  6. What it does to the date. A change that adds two days moves the handover two days.

Lines 2 and 3 are the tedious ones by hand: you have to remember what the approved design was and spot every difference, including the item someone nudged 10 cm. That is the part software should do.

How VanPlot handles it

I built this into the Workshop licence because the comparison is mechanical once the design is the data:

  • Approve freezes the version. Your client designs with you in the editor; when they press Approve this design, the layout as it is then is saved as a frozen version named “Approved by” plus the client’s name, the project status moves to Approved and you get an email. Editing can continue — the approved version stays in History.
  • Compare lists the difference. The Compare with current button opens a change order against the newest approved version (or any saved version you pick): added, removed and changed items with what changed (position, size, cost, weight), plus the Δ weight and Δ cost. Positions are compared to the millimetre, so a nudged cabinet shows up.
  • Print change order prints that comparison as one page; the same page is a section of the Build Pack, next to the quote.
  • Payload and axles are live. Before you send the change, the payload bar and front/rear axle split already show what the shower and the tank do.
  • Labour lives on the quote. Hours per item and your labour rate and parts markup price the Build Pack’s Quote page, so the new version prices itself.

When the client agrees, they approve the new version, which becomes the next baseline. Every change is a version, and every version has a date and a name on it.

The Workshop licence is €299 / $329 one-time for the first 10 workshops (then €499 / $549), with three seats (you plus two colleagues) — see what it includes or go straight to pricing.

FAQ

What is a change order in a van conversion?

A written list of everything that differs from the design the client signed off — items added, removed, moved or resized — with the cost, weight and labour each change adds, which the client approves before the work is done. It turns “can we just add…” into a priced line instead of an unpaid afternoon.

How much weight does adding a shower and a second battery add?

With VanPlot's default catalog parts: a shower cubicle is 30 kg, a shower drain pump 0.9 kg, a second 105 Ah lithium battery 12 kg, and going from a 35 L to a 125 L fresh tank adds 92 kg when full. If the shower replaces a 35 kg wardrobe, the net change is about +100 kg — around 7 % of the 1,405 kg a Ducato L3H2 has before the build starts.

Can moving an item cost money even if no part is added?

Yes. A moved tank or battery has zero parts cost but real hours — new plumbing or cable runs, new fixings, sometimes a reopened floor — and it changes the axle loads. A change order should list moved items with their labour, not only added ones.

When should a workshop freeze the design?

Before ordering parts or cutting anything: the client approves one version, that version is frozen, and every later request is measured against it. Without a frozen baseline there is nothing to compare against, and every change becomes a memory argument.

Does VanPlot produce a change order?

Yes, in Workshop projects. The client approves the design in the editor, which freezes it as an “Approved by …” version; Compare lists what changed since then with the weight and cost delta, and “Print change order” prints it as one page. It comes with the Workshop licence (€299 / $329 one-time for the first 10 workshops).

Your van is waiting. Measure it, then plan it.

In sixty seconds you'll be dragging a bed into a Ducato. Free, in your browser.

Vladimir Šterjoski

Who makes this

I'm Vladimir. I'm planning my own conversion, and none of the tools I tried could tell me whether a layout would fit or what it would do to the rear axle, so I made this one. I work on it alone. If something's wrong or missing, write to me — the address goes to my inbox.

Vladimir Šterjoski

vladimir@vanplot.comWhy I made it