How to price a camper van conversion for a customer: parts, labour, markup, contingency
· 7 min read
A camper van conversion quote is four numbers added up: the parts from the layout's bill of materials, the fitting hours per module times your hourly rate, a markup on the parts, and a contingency for what you cannot see yet — and every one of them comes from the agreed layout, because the size and weight decisions in that layout move all four. A quote written from a sketch prices a van that does not exist yet. A quote written from the layout prices the one you will build. What that layout has to state before the customer approves it is in the spec sheet post.
This post is for conversion workshops and one-person builders who quote for customers. If you are pricing your own build, the cost breakdown is the post you want.
The formula, line by line
| Line | Where the number comes from | What goes wrong |
|---|---|---|
| Parts | The bill of materials: fixtures (heater, fridge, battery, windows) plus stock (ply sheets, timber, cable, pipe, insulation) | Fixtures get priced, stock gets guessed — the sheets nobody counts |
| Labour | Fitting hours per module × your hourly rate | Hours are priced for the cabinet, not for scribing it round a wheel arch |
| Markup | A percentage on parts | Applied to labour too, so the customer pays your margin twice |
| Contingency | An allowance for the unseen: rust, out-of-square bodywork, late changes | Left out, then absorbed — or hidden inside a vague total |
The total is parts + labour + markup + contingency, with VAT added the way your country requires. Then split it into stages: a deposit on approval, a payment when work starts, the rest at handover.
Parts: price the bill of materials, not a guess
Fixtures are easy to price because they have a catalogue number. Stock is where quotes leak. In a large panel van the subfloor and the wall and ceiling lining take more ply sheets than the furniture does, and the furniture sheets split by thickness, so a carcass, a back and a worktop cannot share a sheet — the plywood sheet count works it through layout by layout. Cable and pipe follow from where the battery, the tanks and the heater sit, which is why the run lengths belong to the layout and not to a rule of thumb.
Use your own purchase prices, not retail. The difference between your trade price and the price on the box is part of your margin, and it belongs in the markup line where you can see it.
Labour: hours per module, from your own jobs
There is no published, trustworthy table of how long a shop takes per module, and I am not going to invent one. What exists in this blog is the DIY figure: builders report roughly 250–600 hours for a complete first conversion, with furniture alone at 80–200 hours. A shop with jigs, templates and a bench is much faster than that; how much faster is in your own timesheets.
What a per-module structure gives you is a quote that changes when the layout changes. VanPlot starts each module at a default and expects you to overwrite it:
| Module | VanPlot default fitting hours |
|---|---|
| Kitchen block | 10 |
| Fixed bed / extendable bed | 6 / 8 |
| Wardrobe | 5 |
| Overhead cabinet | 4 |
| Combi heater / diesel heater | 5 / 4 |
| Window | 3 |
| Shower | 12 |
| Solar panel, roof vent, water tank | 2 each |
| Battery | 1.5 |
| Fridge, toilet, water pump | 1 each |
These are starting points for a small shop, not market data. Two things they do not cover: the shell — insulation, floor, lining, cable runs — and anything unusual about the base van. Carry your shell hours as a line of their own; they scale with the van's length and height, not with the furniture.
Markup and contingency
Markup goes on parts, not on labour. Your hourly rate should already contain your overhead and profit. A markup on top of labour charges the customer twice for the same thing and makes your quote look expensive against a shop that prices honestly. VanPlot's quote applies the markup percentage to parts only.
Contingency is for what you cannot see. A new van has fewer unknowns than a used one with a rusty floor under the old ply. DIY builders budget about 10% for redoing mistakes; a shop that has built the same base van ten times needs less on furniture and the same on the metal. Write the contingency into your terms in plain words. VanPlot's quote page has no separate contingency line, so either fold a few percent into the markup or state it in the terms field that prints on the quote.
What contingency should not cover is the customer changing their mind. Once the layout is approved, a second fridge or a moved wall is a change order with its own price, not a cost you absorb.
How size and weight decisions move the number
Every layout decision lands on at least two lines of the quote:
| Decision | Parts | Hours | Weight |
|---|---|---|---|
| Longer or taller base van | More lining sheets, insulation, cable | More shell hours | Heavier shell |
| Lithium instead of AGM | More expensive per Ah | About the same | A 100 Ah lithium battery is ≈12 kg, an AGM ≈28 kg |
| Birch instead of poplar ply | Dearer | Same | Heavier |
| Fixed shower cubicle | Tray, walls, tanks, pump | 12 h default before plumbing | 40–80 kg with the toilet, before water |
| Extra overhead lockers | Sheets and hinges | 4 h each by default | Weight high up |
The weight column matters because a build typically adds 400–700 kg to the empty van, and a layout that runs out of payload is not a cheaper quote — it is a redesign, or an uprating the customer did not budget for. Check the weight before you send the price, not after the van comes back from the weighbridge.
A worked example
Round, illustrative numbers — not a market rate:
| Line | Figure |
|---|---|
| Parts (fixtures + stock) | €10,000 |
| Labour: 140 h × €60/h | €8,400 |
| Markup: 20% on parts | €2,000 |
| Quoted total | €20,400 |
| Deposit 50 / 25 / 25 | €10,200 · €5,100 · €5,100 |
Swap the AGM bank for lithium and the parts line moves; add a shower and parts, hours and weight all move at once. That is the case for pricing from the layout: the customer changes the layout, and the quote follows instead of being redone.
Doing it in VanPlot
The Workshop licence adds a quote page to the Build Pack. In the Build Sheet you set your labour rate, markup on parts, how many days the quote is valid, the deposit split and your terms; in Catalogue & prices you set our cost and our hours per part type, and every quote in the workshop follows when you change one. The quote page lists parts, labour and sell price per line, then the total, validity, deposit and terms, under your logo. Behind it come the weighbridge report, the cut list and, after approval, the change-order sheet against the agreed version.
Your customers can design on your vans at your public shop page and see a live estimate from your prices — rounded down to a "from" figure, rounded to an "about" figure, or hidden. That estimate covers the parts they place and their fitting hours; the shell materials join on the full quote.
The Workshop licence is a one-time $329 / €299 for the first 10 workshops, then $549 / €499, with three seats, you plus two colleagues (checked November 2026). Questions: vladimir@vanplot.com.
FAQ
How do you price a camper van conversion for a customer?
Add four numbers: the parts from the layout's bill of materials (fixtures plus the sheets, timber, cable, pipe and insulation they need), the fitting hours per module times your hourly rate, a markup on the parts, and a contingency for what you cannot see before the panels come off. Quote from an agreed layout, not a sketch, so the parts list and the hours describe the same van.
Should the markup apply to labour as well as parts?
Usually not. Your hourly rate should already carry your overhead and profit; a percentage on top of labour double-charges the customer for the same thing. VanPlot's quote page applies the markup to parts only and prices labour at your rate.
How many hours does a professional van conversion take?
There is no reliable published per-module figure for shops, so use your own job records. As a reference point, DIY builders report roughly 250–600 hours for a complete first build, with furniture alone at 80–200 hours. A shop with templates and a bench is faster; VanPlot's starting defaults (for example 10 h for a kitchen block, 6 h for a fixed bed) are there to be overwritten.
How much contingency should a conversion quote include?
It depends on how much of the van you have not seen. DIY builders budget about 10% for redoing mistakes. A shop that has built the same base van before needs less on furniture; a used van with unknown rust under the floor needs more. Name the contingency in the terms, and price customer changes after approval as change orders instead of eating them.
Can customers see a price while they design?
With the VanPlot Workshop licence, yes: your public shop page shows a live estimate from your own part prices and fitting hours, as a rounded 'from' or 'about' figure, or no figure at all. The full quote with shell materials, validity and deposit schedule is the quote page in the Build Pack you send.